By CJ Jorgensen for AZBEX
Phoenix is continuing its rapid expansion in the data center market, becoming a primary data center hotspot of the West.
Information in the โAmericas Data Center H1 2024 Updateโ released last week by Cushman & Wakefield, shows Phoenix has seen a rapid expansion of absorption within the past two years, having reached 411MW in 2022 and 600MW in 2023. Phoenix saw slightly more absorption in the first half of 2023, but this is likely due to limitations on the delivery of supply.
Phoenixโs absorption in the first half of 2024 was 126MW with 367MW under construction. Phoenix has 957MW in operation with a colocation vacancy rate of 1.3%.
Hyperscalers and colocation providers have been eagerly assessing land sites across the Valley. Both veteran providers and newer prospects are digging their roots deeper into the Phoenix area.
Phoenix itself is in a unique environment that propels the process of becoming the Westโs data center hotspot. โPhoenixโs location offers a distinct advantage by providing low latency connectivity from major tech metros on the West Coast to fast-growing markets in the Southwest,โ Cushman & Wakefield reports. โWith tight vacancy and many options when it comes to providers, Phoenix has quickly become the central data center hub along the West Coastโ
A specific issue for Phoenix-area data center development is the availability of water. Water-cooling technology is one of the most efficient ways to cool high temperatures from intensive AI/HPC workloads. Both state and local governments have tried to combat water overuse by incentivizing the use of air-cooling technologies.
Energy is another benefit Phoenix brings to the table, notably renewable energy. While Phoenix already has an established power grid consisting of 52% natural gas and 45% nuclear, private solar panels have become increasingly prevalent.
Even with the increase of available power sources, it continues to be an ongoing and significant issue in the expansion and creation of more data centers. This, however, is not exclusively limited to Phoenix, as it is one of the more common challenges data center developers are facing.
As was discussed in the 2024 BEX Private Development Summit last month, utility providers Arizona Public Service and Salt River Project are working closely with customer firms across all marketsโbut most specifically data centersโto correctly assess and develop supply and delivery plans for current and projected future needs. (AZBEX, Aug. 9)
While there are considerable limitations and obstacles, Cushman & Wakefieldis strongly positive about Phoenixโs momentum.
Phoenixโs Place in the North American Market
Overall, Phoenix is third in the country regarding overall stock levels with 2.9GW, which is about 15.7% of North Americaโs 18.5GW of operational capacity. Virginia holds the lead by a significant margin, carrying 13.2GW, or about 71.4%.
Phoenix directly follows Atlantaโs 3.8GW in the data collected by C&W and is ahead of Chicagoโs 2.4GW and Dallasโ 2.3GW.
Dallasโ numbers in the first half of 2024 were quite similar to Phoenixโs. Dallas saw a slight edge in both absorption (163MW) and capacity under construction (637.5MW), but it also saw a colocation vacancy rate of 1.4%. Dallasโ operation number trailed at 848MW.
Dallasโ 2023 absorption rates were just less than two-thirds of Phoenixโs, coming in at 386MW.
Other western areas seeing an expansion are Portland + Eastern Oregon, Reno and Salt Lake City.