Two new data center proposals have recently begun the review and approval process across the state.
Arizona has been a high-growth market for the controversial development type for several years, due in part to a tax incentive program started in 2013 under former Gov. Jan Brewer. That program was recently issued a temporary pause under Gov. Katie Hobbs, which triggered a plethora of new applications before the moratorium took effect.
The two recent submissions tracked here come as project proposals under existing master-planned developments, one in Buckeye, and one in Eloy.
Fortescue Buckeye Energy Campus
AZBEX first reported on Fortescue Future Industries’ request to revise a roughly 158-acre portion of a 920-acre former planned hydrogen production hub in Buckeye earlier this year. Those requests referenced a possible future data center. (AZBEX; Feb. 10)
In March, Buckeye City Council approved a rezoning to remove previous restrictions limiting the site to hydrogen production, and the site is now open for other development options.
On Nov. 24, the Buckeye Planning and Zoning Commission will hear Fortescue’s new request, which is for a Conditional Use Permit that will allow development of a three-building, 1.7MSF data center it is calling the Buckeye Energy Campus.
USA Fortescue Future Industries LLC and engineering firm Jacobs are representing Fortescue entity Phoenix Hydrogen Hub LLC in the application process, naming Phoenix Hydrogen Hub as the landowner and applicant. According to the submitted materials, the applicants are “seeking a Conditional Use Permit for a data center with onsite power and accessory uses on Heavy Industrial (I-2) zoned land in the southern end of the city of Buckeye at South 283rd Avenue and West Patterson Road.”
The submittal says the land is adjacent to the Woolsey Peak Substation. The project proposal says the development will construct:
- Three-100 MW IT load capacity data center buildings with associated customer-owned substation, mechanical cooling plant and battery energy storage system,
- 300MW BTM thermal onsite power capacity generation in the form of natural gas reciprocating engines
- Primary onsite high voltage substation,
- Transmission lines connecting project substation to Woolsey Peak Substation for 120 MW grid power and
- Utilities and other linear infrastructure.
Once built and operational, the center would employ between 45 and 100 people full time, depending on the final operational intensity and IT load capacity, according to the submittal.
The description says, “Each data center building is designed with two distinct functional zones: the Data Center (DC) area containing IT equipment, and the DC Administration area containing onsite worker offices. The site layout prioritizes the placement of administrative and employee-oriented spaces near the main entrance to each building, with these areas featuring glazing to enhance visibility and convey a welcoming arrival experience.”
Of the total 1.725MSF total built area, 276KSF would be office space. Building heights are planned for up to 63 feet.
While the final design is not yet complete, the campus plans to use a closed-loop cooling system to minimize water use and will not use cooling towers or evaporative cooling.
The submittal says, “A closed-loop liquid cooling system serving a large data center campus may require an initial fill volume ranging from 500,000 to 2 million gallons. This represents a one-time system fill rather than ongoing consumption.”
It goes on to say limited amounts of additional water will be used from time to time for minor maintenance, equipment servicing, minor system losses and long-term operating adjustments.
According to the staff report, water will be supplied by an existing onsite well previously used for agricultural irrigation. It also notes the closed-loop operating model will use significantly less water than agricultural uses would.
Total installed power generation capacity for the site will be more than 300MW. “Initially, the project will receive approximately 120 MW of electrical service from the Arizona Public Service transmission system via the Woolsey Peak Substation. Electrical service will be provided pursuant to an Energy Supply Agreement negotiated with APS.
“In addition to the 120 MW utility service, the project will include a dedicated behind-the-meter natural gas-fired thermal generation facility capable of supplying approximately 300 MW of primary electrical generation to support the facility’s operations. The generating facility will utilize high-efficiency natural gas reciprocating engine-generator units.”
Future development on the site may include solar energy to help balance the campus’ energy needs with carbon-free generation.
The staff report found the proposal is consistent with the site’s heavy industrial zoning and General Plan land use designation, adding, “Data centers across the country, and especially in Arizona, have garnered significant attention in recent years due to their rapid proliferation and construction near urban and residential areas that have, in some instances, caused land use conflicts. This subject property is ideal for data centers, however, as it is relatively remote, within a future industrial corridor along State Route 85, and located just north of the City of Phoenix landfill. The property’s isolation will mitigate the negative impacts of data centers by allowing excess noise and heat to dissipate prior to impacting residential uses. That said, Lewis Prison is located northeast of the site, and staff has worked with the applicant via stipulation to establish a noise limit of 70dBA LAeq. (one hour) at or beyond the property line, intended to ensure noise from the site will not be louder than ambient traffic noise from SR-85 to minimize impacts to the prison’s staff and inmates.”
Fortescue Future Industries is the owner. Jacobs is the engineer. The design firm and general contractor have not been announced.
Southwest Crossing Phase II
The second proposal would develop seven data center buildings of 160KSF each as Phase II of the Southwest Crossing Data Park at the NWC of Tweedy and Battaglia roads in Eloy.
The proposal comes from developer CRG, the real estate development arm of Clayco, and requests a rezoning and planned area development overlay for the 152 gross-acre property. “The Property is currently zoned I-1 Light Industrial, and this request would rezone it to the I-2 General Industrial Zoning District. The PAD will add a new Data Processing & Hosting Facility use and modify the permitted height for the Facility while maintaining uses allowed under the existing I-2 zoning district,” the submittal says.
The PAD overlay for Phase I was approved in 2025. According to the request, “The proposed PAD overlay has been adapted from the Southwest Crossing PAD Phase I to apply to this Property, which is necessary to add the Data Processing & Hosting Services use as a Permitted use, resulting in a cohesive development framework between the two properties in terms of permitted uses and development standards. The PAD is very limited in scope to add Data Processing & Hosting Services Data Processing & Hosting Services. To offset the increase in building height, the PAD includes several unique architectural guidelines aimed to minimize the perceived visual impacts of a large building.”
The zoning ordinance does not define Data Processing & Hosting Services, so the submittal proposes its own: “A use that’s primary purpose is to provide information technology services, including digital data processing and distribution, web hosting and management, internet and cloud services for applications, networking and security, data and telecommunication storage, backup, recovery, and management, eCommerce transactions, and internet gaming platforms. Data Processing & Hosting Services are typically located in a facility that contains the necessary information technology and computing hardware and software to provide the aforementioned services, including supporting equipment such as generators, water tanks and treatment facilities, electrical switch yards and substations, and related mechanical equipment.”
Buildings would have a maximum height of 80 feet.
The property sits adjacent to the Union Pacific Railroad and several vacant industrial-zoned properties on three sides. It carries an “Employment High” designation under Eloy’s General Plan.
As with nearly all modern data center designs, the facility would rely on closed-loop cooling. The submittal says each building will require an initial fill of 300,000 gallons plus multiple flushings to ensure the system is clean and ready.
“Filling of the buildings’ cooling systems can be metered by the City to ensure that the filling occurs gradually and within daily limits established by the City to ensure the project demands stay well below the available capacity and leave abundant reserves to address emergency situations, system disruptions, fireflow demands, operational contingencies and future growth. Maintenance events requiring discharge of the closed-loop cooling system may occur semi-annually, though such events only require partial evacuation of a building’s cooling system, and not all such maintenance events affect all buildings.”
Maximum daily demand would be between roughly 35,000 and 54,000 gallons/day. “The City has roughly 1.17 million gpd of available capacity in its wells, which means that the maximum daily demand for the project – approximately 0.0348 to 0.0593 million gpd depending on humidification- is only 2.97% and 5.06%, respectively, of the remaining, available supply. As such, no additional groundwater well sources are required to supply the water demands for the Project.”
CRG says it is currently working with the area electrical utility and the 350-acre Project Bella energy generation facility to secure approval of an energy demand analysis and infrastructure design for Phase II’s required 400MW of power. In total, Southwest Crossing will require 800MW, with both phases served by Western Area Power Administration Electrical District 4.
The property owner is the Loretta J. Haugen Trust. CRG Acquisition LLC is the developer. The project engineer is Colliers Engineering & Design, with architectural services provided by LJC Design & Engineering. Bergin, Frakes, Smalley & Oberholtzer is the land use attorney.
The Eloy Planning and Zoning Commission heard a presentation and discussion of the plan at its Nov. 18 meeting. No action was taken.